To ensure that the team remains on schedule, a Gantt Chart was completed for the estimation of when tasks should be completed by. The critical path, shown in red, denotes the chain of tasks that constrains the project the most. All milestones are denoted by a ♦, along with the date. It is estimated that the project will take 101 working days, beginning on November 8, 2023 and ending on May 7, 2024.