Cost Analysis

The cost estimate was performed using public works bids from related projects in the Flagstaff, Coconino County, and Phoenix areas.  The costs are materials and installation costs only.  No construction staging, material removal, administration, or project management costs were considered in the cost analysis.  Also, a 20% contingence was added due to the project only being a 60% design.

McConnell Drive Pedestrian Bridge

Item

UOM

Quantity

Unit Cost

Total

Structural Concrete

cu. yd.

78.13

750.00

$58,596.75

Asphalt (2")

sq. yd.

127.09

45.00

$5,719.05

Sidewalk Concrete

sf

5092.80

6.17

$31,442.95

Steel Reinforcement

lb

6665.39

1.00

$6,665.39

Chainlink Fence w/ Posts

lf

330.60

80.67

$26,669.50

8' Iron Fence

lf

60.60

35.00

$2,121.00

Fill

cu. yd.

751.93

62.67

$47,123.45

Prestressed Slab

lf

326.80

135.00

$44,118.00

Masonry Blocks

sf

2018.28

9.29

$18,750.28

Steel Strips

lb

2591.00

0.59

$1,527.84

Brick Veneer

sf

3302.24

36.00

$118,880.64

Contingencies

%

30.00

 

$72,820.26

 

 

 

Total:

$434,435.12