September 9,2002 -- Project Description and Team information.

October 8, 2002 -- Status Report Due.

October 15, 2002 -- Client Contact.

October 29, 2002-- Project presentation (Presenting design report to class)

November 26,2002 -- Proposal Presentation.

December 7, 2002 -- Proposal Acceptance document/ Peer evaluation / Engineering Notebook  all  due.

February  5,2003 -- Mathematical Model.

March 6,2003 -- CAD Model.

April 20,2003 -- Final Design due.

April 25,2003 -- Capstone Presentation.

May 2, 2003 -- Final report should be done.