Final Project
HOME Team Members Client Project Description Final project Deliverables Schedule/Milestones Invitation Final presentation Photos
![]()
|
Design Choice |
Advantages |
| CONCENTRIC DUCT
|
nRelatively Low Installation Cost
nLow Material Costs
nLow Impact on Existing Systems
nHigh Payback on Investment
nLow Maintenance Costs
|
CAD MODEL : Temperature Distribution throughout duct

FINAL DESIGN : How we are going to recapture the heat with our design tube.

5-Year Summary Savings Based on our Calculations.
|
Force Convention |
$7890 |
|
Radiation |
$540 |
|
Drag loss |
-$270 |
|
Insulation Loss |
-$2 |
|
Total |
$8250 |
Project Summary :
|
Energy Savings |
554,000 KBtu/Year |
|
Evaporation rate improves |
1% daily |
|
Payback of Project |
1.3 years |
|
Implementation Cost |
a. Labor -$1650 b. Materials -$350 Total - $2000.00 |
|
Team Budget |
Documentation -$150 |
Conclusion: