Deliverable Name Description Due Date Delivered Document
Team Inventory Document with information about all team members. September 24, 2018
Team Standards Specifications of standards agreed upon and to be followed by all members of the team. September 24, 2018
Mini-Intro Brief introductory presentation of our capstone project. October 4, 2018
Technological Feasibility Exploration of options for solving the client's issue and the feasibility of the different options. November 6, 2018
Design Review 1 10-12 minute presentation outlining the design of our solution for the product to this point. November 20, 2018
Requirements Specifications Document summarizing the requirements gathered and evaluated to complete
the development of this project.
December 4, 2018
Communication Strategy Memo A memo to higlhight team communications and scheduling January 17, 2019
Software Design Document highlighting the design, architecture, and modules being used February 18, 2019
Design Review 2 10-12 minute presentation outlining the design of our solution for the product to this point. February 28, 2019
Software Testing Plan Detailed testing plan that highlights how we will test our product. April 2, 2019
Design Review 3 15-16 minute presentation regarding the testing and refinement of our product. April 11, 2019
UGRADS Presentation 15-16 minute presentation to an audience at the Undergraduate Symposium to describe our product. April 26, 2019
UGRADS Poster A poster that describes our product to those on the floor of the Undergraduate Symposium. April 26, 2019
Team Reflection Document Document where the team describes how the project went over the past year. May 9, 2019
User Manual Part of the final delivery, a user manual that describes how to use the software and download the correct technologies in order to continue the work of our product. May 9, 2019
Final Report A summary of our project and the technologies used in our product. May 9, 2019