This is a brief review of the summer semester performance and possible improvments to concerns.
This is the preliminary proposal file submitted at the halfway point in the project. Since then changes have been made which can be seen in the Current Design tab.
Click here to view the team's photo gallery containing CAD model pictures as well as physical designs or testing done concerning the project.
There are links to Aaron Curley's individual analyses and self learnings.
These are links to Yanchu Du's individual analyses and self learnings.
These are links to Richard Hamilton's individual analyses about power consumption as well as self learnings about 3D printing and Soldering.
These are links to Hunter Kea's individual analysis and self learning.
These are links to Alfred Serventi's Self learnings and Individual Analysis.
This document descripes any modified engineering requirements based on new designs or information about the design. This documents also covers testing procedures based around new designs or engineering requirments.
This is the team's first implementation memo as the team's budget was being resolved and calculated. This memo documents major design changes before building starts such as material selection and needed manufacturing.
This is the team's second implementation memo as physical building of the project just began. This memo discusses manufacturing needed for the project as well as design changes that occured during prototyping.
This is the team's midpoint presentation as material purchasing was beginning. This presentation does not show any bulding that had occured and any building progress should be seen in the photo gallery section above.
This is where the team's updated bill of materials and budgeting can be found.
This brief manual discusses maintanence of the system and any troubleshooting steps the team could forsee the client needing.
The team's ifnal presenation for the fall 2020 semester. As of this presentation, the project is over fo the team.