The schedule for the A286 group, showing our phases and milestones.

Schedule

  • Phase 1 (Oct 8 - Oct 29)
    • Microcontroller specification sheet
  • Phase 2 (Oct 29 - Nov 8)
    • Excel sheet with motor and sensor choices
  • Phase 3 (Nov 8 - Dec 5)
    • List of parts
    • Fully defined i/o system
  • Phase 4 (Dec 5 - Dec 12)
    • Materials chosen
  • Phase 5 (Jan 15 - Jan 31)
    • Testing of electrical components
    • Programming library
  • Phase 6 (Jan 31 - Feb 29)
    • Parts fabricated
  • Phase 7 (Feb 29 - March 29)
    • Casings designed
    • Field testing of parts
  • Phase 8 (March 29 - April 19)
    • Documentation
    • Design of packaging