Team Charter
Introduces team and assigns roles - Complete 1.18.22
Reports
Introduces team and assigns roles - Complete 1.18.22
Introduces problem, design and begins selection process - Complete 3.20.22
Refines problem, presents prototype, design justification and validation and steps moving forward - Complete 4.16.22
Presents a force analysis on the ball-lock mechanism in the final design - leads to geometric optimization and spring selection for final model - Complete 3.20.22
Answers a few key questions regarding activating the nitinol wire in the hold down and release mechanism design - Complete 3.20.22
Presents a force analysis on the pin protruding from the HDRM design - Complete 3.20.22
Reflection and planning for rest of project - Complete 9.2.22
Performs a force analysis using equations to model a Nitinol Spring - Complete 9.16.22
Report compiling resting results - Complete 12.2.22
Final Report compiling work from both semesters - Complete 12.4.22
Document outlining assembly, disassembly, operation, maintenance and troubleshooting of the final product. - Complete 12.11.22