The Project Gantt Chart above outlines the project's approximate schedule. The project is currently schedule to begin on January 13, 2024 and be completed on May 6, 2024. This accounts for 114 working days. The project's critical path is denoted by task in red. These tasks must be finished as scheduled to ensure the project remains on track.