CELS Engineering

Project Information

Gantt Chart Staffing Cost of Engineering Services Project Location Project Constraints Project Tasks

Project Description

The project focuses on a segment of JWP Blvd. situated between two key intersections. JWP originates at the Interstate 17 (I-17) off-ramp and extends approximately 4 miles eastward. Specifically, this project centers on the 1.5-mile section between South Pulliam Dr. and Lake Mary Rd., traversing a region characterized by dense forests and challenging terrain.

Project Location

The project is located in the west portion of Flagstaff, Arizona. The project site lies south of where the I-17 and I-40 intersect and north of Flagstaff Pulliam Airport.

Project Vicinity Map
Project Location Map
Back to Top

Project Constraints

This project faces several constraints. Firstly, the road's route must circumvent a VHF (Very High Frequency Omnidirectional) device to avoid interference with operations at Flagstaff Pulliam Airport. While the specific path of the road can be adjusted, the starting and ending points remain fixed due to predetermined intersection requirements. Additionally, Flagstaff is prone to severe weather conditions, particularly during winter, which poses a challenge by potentially hindering or slowing down the progress of the project.
Back to Top

Project Tasks

Back to Top

Gantt Chart

The Gantt chart below depicts the projects schedule. The project is scheduled to commence on January 16, 2024 with a total task duration of 73 days, excluding weekends. Task 1: Research and Data Collection, Task 2: Site Investigation, and Task 3: Hydrologic Analysis, are planned for completion by February 16, 2024, reaching the 30% submittal milestone. Task 4: Hydraulic Analysis and Task 5: Roadway Design are targeted for completion by March 15, 2024, marking the 60% submittal milestone. Task 6: Construction Plans, Task 7: Economic Analysis, and Task 8: Impact Analysis are expected to be finished by April 19, 2024, reaching the 90% submittal milestone. The final presentation will need to be prepared by April 26, 2024, and will encompass the entirety of the project. The final submittal is slated for May 2, 2024, containing a fully detailed report.
Back to Top

Staffing

The staffing plan provides an overview of the required personnel for the execution of engineering services. All staffing requirements and time allocations are calculated and assigned according to each staff member's respective qualifications and overall contribution to the project’s completion.
Back to Top

Cost of Engineering Services

The cost of engineering services is the management of project cost, involving estimating, cost control, cost forecasting, investment, and risk analysis.