1

   Data Collection

Fri 9/4/15

Tue 11/3/15

1.1

      Site Evaluation

Fri 9/4/15

Thu 9/10/15

1.2

      Topographic Survey

Fri 9/11/15

Mon 9/14/15

1.3

      Client Meeting

Tue 11/3/15

Tue 11/3/15

2

Roadway Design Guidelines

Mon 11/2/15

Fri 12/11/15

2.1

      Research guidelines

Mon 11/2/15

Fri 11/6/15

3

   Data Analysis

Mon 11/2/15

Fri 3/4/16

3.1

      Survey Data

Tue 11/3/15

Tue 11/3/15

3.2

      Traffic Statistics

Wed 11/4/15

Tue 11/10/15

3.3

Level of Service: TWSC

Thu 11/12/15

Wed 11/18/15

3.4

LOS: Roundabout

Mon 2/22/16

Fri 3/4/16

4

   Site Design

Tue 1/19/16

Fri 3/4/16

4.1

      Roundabout

Tue 1/19/16

Mon 2/29/16

4.1.1

         Geometry

Tue 1/19/16

Sun 2/21/16

4.1.2

         Grading

Tue 2/9/16

Sun 2/21/16

4.1.3

         Striping

Mon 2/22/16

Thu 3/11/16

4.1.4

         Signage

Fri 2/26/16

Mon 3/11/16

4.2

      Site Development

Mon 1/25/16

Fri 2/26/16

4.2.1

         Drainage

Mon 2/29/16

Fri 3/25/16

4.2.2

         Landscaping

Sat 2/29/16

Wed 3/25/16

4.2.3

Pedestrian Consideration

Thu 3/10/16

Thu 3/25/16

5

   Economics

Mon 2/29/16

Fri 4/1/16

5.1

      Construction Costs

Mon 3/5/16

Wed 4/1/16

5.2

      Benefits

Mon 3/7/16

Fri 4/1/16

5.3

      Impacts

Mon 3/21/16

Fri 4/1/16

6

   Project Management

Tue 10/27/15

Thu 5/12/16

6.1

      Project Schedule

Mon 11/16/15

Fri 11/20/15

6.2

      50% Design Report

Fri 3/11/16

Fri 3/11/16

6.3

      Final Design Report

Fri 4/29/16

Thu 5/12/16

6.4

      Final Presentation

Fri 4/29/16

Fri 4/29/16

6.5

      Website

Mon 11/23/15

Fri 12/4/15

 

Milestone

Item Start Date Finished Date
Data Collection 9/10/2015 11/17/2015
Data Analysis 11/3/2015 4/2/2016
Site Design 2/21/2016 4/15/2016
Site Development 3/25/2016 4/1/2016
50% Design Report 3/11/2016 3/11/2016
Final Report/ Presentation 4/29/2016 4/29/2016

View details »

<>