Home | About | Bridge Technology | Site Location | Project Background | Design Process | Final Design
Design Process
The design process for this Town Lattice Truss
Bridge included research, a review of applicable codes, demand
calculations, design, and confirmation of the results using SAP
2000.
Before any calculations or design could be
accomplished, preliminary research had to be conducted. The design
team had to become familiar with the engineering properties of wood
and wood processing because the client requested the use of
Ponderosa Pine from his own property for this project.
The design team also had to become familiar with Town Lattice
Trusses and general bridge components necessary for a combined
vehicular and pedestrian bridge.
Communication with the City of Flagstaff and
the project advisor resulted in the recommendation of design manuals
and documents to use as references.
These included AASHTO Standard Specifications for Highway
Bridges 2002 (17th Edition), ASCE/SEI 7-05: Minimum Design Loads for
Buildings and Other Structures, 2010 ADA Standards for Accessible
Design, and the City of Flagstaff Building Codes and Engineering
Standards. The codes
were reviewed to find design information.
With the use of applicable codes, demand
calculations were performed for the bridge and thus finding the
resulting forces. AASHTO
was used to determine the allowable stress of the timber.
Based on the demand and available capacities, bridge
components were designed and sized.
The Town Lattice Truss Bridge was drawn in SAP
2000 to the dimensions determined by the design team.
The bridge was then loaded to determine the forces acting in
each member, and these values were used to confirm the allowable
stress in each member was not exceeded.
SAP 2000 was also used to determine the shear force each
connection joint must sustain.
Significant Milestone
·
30% Design -
2/21/11
·
Scale Model -
4/28/11
·
60% Design -
4/28/11
·
Presentation -
4/29/11
Project Obstacle
Some of the obstacles that Ponderosa Engineering has overcome were
due to the steep learning curve for the project.
The team was unfamiliar with
wood and bridge design; therefore more hours were allotted to
research to further our understanding of these concepts, which
caused a delay in our schedule. The
team also encountered another delay due to unfamiliarity of detailed
design for a timber bridge and time demand associated with the
coming up to speed on these aspects. Ponderosa Engineering got back
on schedule by holding extended meetings to complete the 60% of
bridge design, website, UGRAD poster, and scale model.
Ponderosa Engineering and BGK Engineering had the unique challenge
of concurrently developing designs that were dependent on one
another. As a result,
each group had to maintain effective communication with the other to
minimalize delays.