March 2004

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
  1 2
Presentation on progress
3 4 5
Draft Status Report due
6
7 8 9
Final Status Report due, Max232 tested and ordered
10 11 12 13
14 15 16
Spring Break
17 18 19 20
21 22 23
All major components received, testing of transciever begun
24 25 26 27
Transciever communication problem fixed, commands must be sent as one string
28 29 30
Meeting with Dr. Scott on progress
31