Gantt Chart

Work Tasks Wk1 Wk2 Wk3 Wk4 Wk5 Wk6
1. Finish Proposal
Specs
Research
Schedule xxxx
Architecture _xxxxx
2. Validate with Sponsor:
Meet with Sponsor ___x
Validate Website xxx
3. Do Detailed Software Design
Data ___xx
Processes xxx
Objects ___xx
4. Coding and Implementation
Interface Class and Headers xxx
PPF_Logic Prototype __xxxxxx
Parallel_Wrapper xxxxxxx
PPF_Logic with Wrapper xxxxx
Work Tasks Wk7 Wk8 Wk9 wk10 Wk11
PPF_Logic with Wrapper xxx
Statistics and Timer __xxx
5. Finish Code
Testing xxxxxxxxxxxxxxx
Revision xxxxxxxxxxxxxxx
Review xxxxxxxxxxxxxxx
6. Finish documentation
Code Documentation xxxxx
Project Usage Documentation xxxxx