The following project table is a planned schedule for spring semester, 2000.
Work Tasks | Planned Start | Planned Complete |
1. Finish Proposal | ||
Specs | finished | finished |
Research | finished | finished |
Schedule | wk1, d2 | wk1, d4 |
Architecture | wk1,d2 | wk1, d5 |
2. Validate with Sponsor: | ||
Meet with Sponsor | wk2,d3 | wk2,d3 |
Validate Web-site | wk2,d1 | wk2,d3 |
3. Do Detailed Software Design | ||
Data | wk2,d4 | wk2 d6 |
Processes | wk3,d1 | wk3,d3 |
Objects | wk3,d3 | wk3,d5 |
4. Coding and Implementation | ||
Interface Class and Headers | wk4,d1 | wk4,d3 |
PPF_Logic Prototype | wk4,d3 | wk5,d3 |
Parallel_Wrapper | wk5,d1 | wk6,d1 |
PPF_Logic with Wrapper | wk6,d1 | wk7,d3 |
Statistics and Timer | wk7,d3 | wk8,d1 |
5. Finish Code | ||
Testing | wk8,d1 | wk10,d5 |
Revision | wk8,d1 | wk10,d5 |
Review | wk8,d1 | wk10,d5 |
6. Finish documentation | ||
Code Documentation | wk11,d1 | wk11,d5 |
Project Usage Documentation | wk11,d1 | wk11,d5 |