Project Table

The following project table is a planned schedule for spring semester, 2000.

Work Tasks Planned Start Planned Complete
1. Finish Proposal
Specs finished finished
Research finished finished
Schedule wk1, d2 wk1, d4
Architecture wk1,d2 wk1, d5
2. Validate with Sponsor:
Meet with Sponsor wk2,d3 wk2,d3
Validate Web-site wk2,d1 wk2,d3
3. Do Detailed Software Design
Data wk2,d4 wk2 d6
Processes wk3,d1 wk3,d3
Objects wk3,d3 wk3,d5
4. Coding and Implementation
Interface Class and Headers wk4,d1wk4,d3
PPF_Logic Prototype wk4,d3 wk5,d3
Parallel_Wrapper wk5,d1 wk6,d1
PPF_Logic with Wrapper wk6,d1 wk7,d3
Statistics and Timer wk7,d3 wk8,d1
5. Finish Code
Testing wk8,d1 wk10,d5
Revision wk8,d1 wk10,d5
Review wk8,d1 wk10,d5
6. Finish documentation
Code Documentation wk11,d1 wk11,d5
Project Usage Documentation wk11,d1 wk11,d5