Basic Website Milestone (February 6)
- There will be a website, illustrating the general structure of the website.
- Placeholder pages will contain a description of the eventual functionality of the page.
- The page will also include one or more drag and drop demos, illustrating the ability to use drag and drop, and to discern order from draggable items.
- The goal of the basic build will be to have a starting prototype.
Alpha Website Milestone (February 27)
- Page navigation will be fully functional.
- Playable templates will be working.
- Basic games will be designable using the adventure designer.
- Preferences will be changeable, and video will stream.
- The overall goal of the alpha build will be to have an ugly but functional product satisfying most features.
Beta Website Milestone (March 13)
- The basic website will contain a fair amount of polish.
- The ability to upload audio will be available.
- The adventure designer will be able to display a module graphically.
- All templates are available and fully implemented.
- The goal of the beta website is to have an almost completed final product to test on users.
RC 1 Website Milestone (March 27)
- The website will contain a high degree of polish.
- The website will support pre-caching of videos.
- A dialogue playback of an adventure will be available to users.
- All templates and their controls will be setup.
Final Website, Capstone (April 16)
- There is some included fallback time for schedule slippage.
- There is some included time for acceptance testing and recoding.