The Project Gantt Chart below outlines the project's approximate schedule. The project is currently schedule to begin on September 1, 2025 and be completed on May 4, 2026. This accounts for 173 working days. The project's critical path is denoted by task in red. These tasks must be finished as scheduled to ensure the project remains on track.
Below is the cost breakdown by task and role for billable services
Below is the total cost of engineering services including the billable services and resources costs. The expected total cost is $61,936