Project Overview

This project is an evaluation of the Continental Country Club golf course in Flagstaff, AZ, focused on improving water management and course resilience. By combining advanced design, hydraulic modeling, drone surveying, and soil analysis, the project aims to reduce water use, control erosion, support sustainable operations while protecting the environment, and addressing client priorities.

Project Constraints

The proposed improvements cannot interfere with golf club operations. This includes site investigations, construction phases, and flood mitigations.

Tasks 

The major tasks needed to complete the project is listed below. To see the tasks breakdown check out our documents page!

Task 1: Research & Data Collection
Task 2: Geotechnical Analysis
Task 3: Site Investigation
Task 4: Topographic Map

Task 5: Hydrologic Analysis
Task 6:Hydraulic Analysis

Task 7: Construction Cost
Task 8: Alternative Solutions

Task 9: Plan Set
Task 10: Project Impacts

Task 11: Project Management
Task 12: Deliverables

Gantt Chart

A Gantt Chart was created for ease of tracking dates and times for each deliverable. Click the icon below to see it in it's entirety.

Staffing

A Staffing Chart was created to demonstrate the amount of work each staff member will be doing for this capstone. Click the icon below to see the full chart.

Cost of Engineering Services

A Cost of Engineering Services table was created to illustrate the amount each service of the project would cost and the cost of the project in total. Click the icon below to check it out!