Design-Build and Results

Preliminary Design Final Analysis and Design Cost of Construction Competition Results

Code Analysis

Part of the iteration was to analyze whether the bridge was able to withstand loading. The bridge was analyzed for tensile and compressive forces. Upon review, all members were able to withstand with the worst demand to capacity ratio at 0.72. 

Vertical and Lateral Deflection

The bridge was also analyzed for vertical and lateral deflection. The team determined for the vertical deflection there would be a stricter tolerance on the deflection to anticipate fabrication errors. Therefore, the team ensured that every location with of deflection of greater than 0.5 inches would not meet the team's specification. The aggregate deflection was what was required for the competition, therefore the team also analyzed the expected aggregate deflection for the bridge at the worst case loading. 

Connection Design

The connection design utilized the worst case loading forces within all members to determine the demand for each connection. Using iterations, each critical connection was analyzed for different failure modes for bolted connections. Below shows some of the critical connections that span throughout the bridge and the color coded demand with tension being red and compression as blue. As the bridge is symmetrical, the bridge was analyzed with critical member demand and the capacity of the connections is seen in the table below. 

Fabrication

This project required the team to produces shop drawings to begin the fabrication process. Following the 2-D Shop drawings, the team was responsible for cutting and welding of the bridge. Some of the bridge was welded by the local high school to provide an educational opportunity.

shop drawings

Cost of Construction

The cost of the construction includes the transportation requirements for the materials along with all the shop drawing and fabrications costs totaling $17,155.

1.0 Travel Costs  No. Unit Unit Cost Cost
Rental Truck 5 Days $129 $645
Truck Driving Mileage $1,232 Miles N/A $548
Rental Van $3 Days $48 $145
Van Driving Mileage  $1,100 Miles N/A $490
Hotel $9 Person Nights $113 $1,017
Per Diem $18 Days $50 $900
3.0 Subcontract Hours Rate, $/hr Cost
Fabrication 100 92 $9,219
4.0 Miscellaneous No. Unit Unit Cost Cost
Supplies  $3,988 $ N/A $3,988
Equipment $192 $ N/A $192
Total $17,155

ISWS Competition 

The competition help April 11th-12th is when the team tested their bridge in the vertical and lateral load competition. The following were the results of the competition. Despite the outcome, the team had valuable lessons learned to continue onto future capstone teams. 

Competition Photos By: Kylie Hanson

Want to see our full construction?

Scroll Back to Top