Photo Credit: Estevan LaTurco
The goal of this project is to design a parking lot that will have available parking for the increasing demand of more trucks.
The Purina Site Design Project is located on Nestle Purina Drive in Flagstaff, Arizona.
Due to unforseen circumstances with the COVID-19 outbreak, the team is limited to in-person meetings and full experience of an engineering capstone.
Task 1: Existing Site Due Diligence
1.1: Gather Codes/
Standards
1.2: Obtain and
Review Existing Site Data
Task 2: Site
Investigation
2.1: Field
Observations and Photos
2.2: Soil Sampling
2.3: Traffic Counts
Task 3: Soil Analysis
3.1: Lab Access
3.2: Moisture
Content
3.3: Sieve Analysis
3.4: Hydrometer Test
3.5: Consolidated
Undrained
3.6: Direct Shear
3.7: Triaxial
Compression Test
Task 4: Hydrology
Analysis
4.1: Watershed
Analysis
4.2: Time of
Concentration
4.3: Rational Runoff
Calculation
Task 5: Parking Lot
Design
5.1: Determine Lot
Size
5.2: Determine
Slopes
5.3: Striping
Design/ Signage
5.4: Parking Lot
Safety Measures
Task 6: Hydraulic
Analysis
6.1: Open channel
Design
6.2: Culvert design
6.3: Detention
Analysis
Task 7: Constructin
Cost Estimates
7.1: Site
Development Costs
7.2:
Hydrology/Hydraulic Costs
Task 8: Impact Analysis
8.1: Enviornmental
Analysis
8.2: Economical
Analysis
8.3: Social Analysis
Task 9: Deliverables
9.1: 30% Deliverable
9.2: 60% Deliverable
9.3: 90% Deliverable
9.4: Final
Deliverable
Task 10: Progect
Management
The Gantt Chart demonstrates the time per task scheduled in order to complete the engineering services. The Critical Path is denoted by tasks that are in red.
The Staffing Matrix shows the recommended hours per task per role.
The following table shows the payrate of each role, the payrate of each supply and the total amount of the engineering services.