Photo Credit: Zach Keith
project location project tasks project constraints project DECISION MATRIX & DESIGN project GANTT CHART

Project Location

The project site is located in Flagstaff, Arizona, along South Pulliam Dr and near the Flagstaff Municipal Airport. 

Photo Credit: Zach Keith

Trailhead With Respect to Residential Area

Existing Parking Lot Area

Project Constraints

COVID-19
Social distancing policies were followed by the team according to CDC and NAU guidelines. The team included all restrictions for the participants to follow closely. 

Tasks

The major tasks of the project are listed below. The full version are listed in Documents page. 

Task 1: Site Investigation 
Task 2: Surveying
Task 3: Hydrological and Hydraulic Analysis
Task 4: Geotechnical Analysis
Task 5: Site Design
Task 6: Hydraulic Design
Task 7: Project Impact Analysis
Task 8: Project Deliverables
Task 9: Project Management

Gantt Chart

The team assembled a schedule in a professional Gantt Chart format for ease of tracking dates and times for each deliverable. 

Design Alternatives and Final Design

Decision Matrix

Based upon the decision matrix below, the team decided upon Design 1 as the final design. This design encapsulates the best efforts to keep ingress and egress to a reasonable geometry while retaining the culvert’s stormwater conveyance ability, even with the addition of asphalt, and improving the overall parking layout for users.