Constraints
The project's constraints are to eliminate flooding from the flooding area seen above (red) and transport the water across Pine Knoll Dr. for grey water utilization.
Schedule of Tasks
The tasks necessary to complete the project are listed in the Gantt Chart below, displaying the team's schedule.
Design Alternatives
The figures below represent the three alternatives
considered to mitage flooding from Rolle Activity Center:
Alternative #1: Culvert Design
Alternative #2: Well and Sump Pump Design
Alternative #3: Regrade Design
Final Design
The final design selected was the well and sump pump design due to it meeting both constraints of mitagating flooding from Rolle Activity Center and transporting the water across Pine Knoll Dr. for grey water utilization to irrigate a proposed garden.
Design Plan Set
Fall 2017
Task Hours / Consulting Cost
Fall 2017