MARS Consultants

 

Project Information

Identification of Erosion Source

Based on the analysis performed in this project, the source of erosion is most likely due to the composition of the top layer of the cap. The analysis performed by MARS Consultants found that the top two feet of the cap is composed primarily of sand, with no topsoil or drainage layers as specified in the original design. The sand performs adequately as an infiltration layer, but without a gravel layer there is nothing to convey the infiltrated water out of the cap. Additionally, sandy soil is a poor growth medium, so the absence of a topsoil layer is likely why the initial hydroseeding failed. A comparison between the original design and the observed design can be seen below.

Our analysis shows that the geometry of the cap, runoff from the adjacent hill, and the shear strength of the soil do not significantly contribute to erosion of the cap. Details of this analysis can be seen in the final design report.

Constraints

The main constraint for this project was price. The BLM was unable to support any project with an initial capital cost of over $200,000. In order to meet this constraint, MARS Consultants opted to recycle materials wherever possible in design alternatives to reduce material and transportation costs.

Design Alternatives

Three possible design alternatives were created by MARS Consultants. A description of each design can be seen below.

Each design was evaluated based on initial cost, maintenance costs, aesthetics, and maintenance. As can be seen in the decision matrix below, Alternative 3 received a low score due to its high initial cost. Alternative 2 was chosen because it was discovered that the average side slope of that design was the same as the slope called for in Alternative 1, meaning that it would perform the same in that regard.

Final Design

The final design specifies three rip-rap channels on the cap, located where the worst erosion was observed. The excess sand is used to alter the geometry of the cap to create these channels. The design specifies a 6 inch gravel followed by a sand layer of varying depth to achieve the desired geometry. 12 inches of top soil is placed on top of the sand to provide a growth medium for the hydroseeding. Renderings of the final design, typical channel cross section, and layering details can be seen below.

Channel Cross section

Layer Details

Cost Estimate

Schedule and Hours

Hour Log

Schedule