Project Engineer | Civil Engineer | Environmental Engineer | Administrative | |
Research (hrs) | 18 | 24 | 41 | 0 |
Modeling (hrs) | 13 | 24 | 126 | 0 |
Analysis (hrs) | 72 | 44 | 47.5 | 0 |
Design (hrs) | 11.5 | 72 | 7 | 0 |
Documentation (hrs) | 8 | 9 | 37.5 | 60 |
Meetings (hrs) | 22 | 36 | 23 | 34 |
Total per Personnel (hrs) | 144.5 | 209 | 282 | 94 |
Total (hrs) | 730 |
The table above shows the total personnel hours spent on the capstone project. The project has four main positions: project engineer, civil engineer, environmental engineer, and administrative.
Project Engineer | Civil Engineer | Environmental Engineer | Administrative | |
Total Hours | 144.5 | 209 | 282 | 94 |
Pay Scale | $170 | $60 | $60 | $45 |
Cost | $24,565 | $12,540 | $16,920 | $4,230 |
Total Personnel | $58,255 | Estimated | $59,000 | |
Rock Armoring | $39,000 | ADOT Program and Project Management | ||
Total | $97,255 | Billed | $98,000 |
The table above shows the total personnel cost and material cost for the rock armoring. The estimated value from last semester for personnel costs was $59,000. The actual cost for personnel is $58,255. The rock armoring was estimated to cost $39,000 which was obtained from the ADOT Program and Project Management. The ADOT Program and Project Management service was used to obtain the bid history of rock armoring.
Quoted Price | Service Company | |||
Three-sided Bridge | $150,000 | Contech | ||
Total | $150,000 |