Project Milestones

·        12/07/02 - RMST will present the design proposal to Eric Myers and Steve Larimore of Raytheon Missile Systems.

·        12/13/02 to 01/13/03 – Winter Break

·        01/13/03 to 02/15/03 – RMST will continue design phase.

·        02/15/03 – Design will be finalized.

·        02/16/03 to 04/01/03 – Prototype will be built.

·        03/12/03- Design review presentation

·        04/02/03 to 04/20/03 – Structural and safety testing

·        04/23/03 – Final design presentation

·        04/25/03 – Capstone conference at NAU

·        Tentative 04/25/03 – Final design presentation to Raytheon Missile Systems.

·        05/02/03 – RMST’s web page will be finalized.

·        05/05/03 – RMST’s final design document will be submitted.

 

Project Schedule