Project Overview
Project Milestones
·
12/07/02
- RMST will present the design proposal to Eric Myers and Steve Larimore of
Raytheon Missile Systems.
·
12/13/02 to 01/13/03
Winter Break
·
01/13/03 to 02/15/03
RMST will continue design phase.
·
02/15/03
Design will be finalized.
·
02/16/03 to 04/01/03
Prototype will be built.
·
03/12/03-
Design review presentation
·
04/02/03 to 04/20/03
Structural and safety testing
·
04/23/03
Final design presentation
·
04/25/03
Capstone conference at NAU
·
Tentative 04/25/03
Final design presentation to Raytheon Missile Systems.
·
05/02/03
RMSTs web page will be finalized.
· 05/05/03 RMSTs final design document will be submitted.