ID |
Task Name
|
Duration |
Start |
Finish |
1 |
Documentation
|
142 days |
Wed 10/6/99 |
Thu 4/20/00 |
2 |
Test Document
|
58 days |
Tue 2/1/00 |
Thu 4/20/00 |
3 |
Final 1st Client Status Report
|
6 days |
Tue 2/1/00 |
Tue 2/8/00 |
4 |
Draft 2nd Client Status Report
|
6 days |
Tue 3/21/00 |
Tue 3/28/00 |
5 |
Final 2nd Client Status Report
|
7 days |
Mon 3/27/00 |
Tue 4/4/00 |
6 |
Draft Final Report
|
6 days |
Tue 4/11/00 |
Tue 4/18/00 |
7 |
Linear/DSP
|
120 days |
Mon 10/11/99 |
Fri 3/24/00 |
8 |
Web Development Software
|
40 days |
Mon 10/11/99 |
Sun 12/5/99 |
9 |
Digital to Analog Converter
|
38 days |
Mon 10/11/99 |
Wed 12/1/99 |
10 |
Analog to Digital Converter
|
38 days |
Mon 10/11/99 |
Wed 12/1/99 |
11 |
Programmable Gain Amplifier
|
38 days |
Mon 10/11/99 |
Wed 12/1/99 |
12 |
Strain Gauge
|
16 days |
Mon 10/11/99 |
Mon 11/1/99 |
13 |
Input/Output
|
110 days |
Mon 10/11/99 |
Fri 3/10/00 |
14 |
Final MC Code
|
139 days |
Mon 10/11/99 |
Thu 4/20/00 |
15 |
MS Project Plan
|
4 days |
Wed 10/6/99 |
Mon 10/11/99 |
16 |
Design Plan
|
4 days |
Wed 10/6/99 |
Mon 10/11/99 |
17 |
Client Satus Report
|
3 days |
Thu 10/21/99 |
Mon 10/25/99 |
18 |
Draft Proposal
|
11 days |
Mon 11/8/99 |
Mon 11/22/99 |
19 |
Chip Documentation
|
19 days |
Wed 10/6/99 |
Mon 11/1/99 |
20 |
Final Proposal
|
1 day |
Mon 11/29/99 |
Mon 11/29/99 |
21 |
Proposal Acceptance
|
1 day |
Mon 12/6/99 |
Mon 12/6/99 |
22 |
Testing
|
98 days |
Thu 11/25/99 |
Mon 4/10/00 |
23 |
Final Test
|
11 days |
Mon 3/27/00 |
Mon 4/10/00 |
24 |
Microcontroller Test
|
6 days |
Tue 3/14/00 |
Tue 3/21/00 |
25 |
SG Simulation Test
|
5 days |
Thu 11/25/99 |
Wed 12/1/99 |
26 |
Communication
|
125 days |
Mon 10/11/99 |
Fri 3/31/00 |
27 |
Initial Client Contact
|
9 days |
Tue 10/12/99 |
Fri 10/22/99 |
28 |
Internal Project Review 1
|
5 days |
Mon 10/11/99 |
Fri 10/15/99 |
29 |
Internal Project Review 2
|
1 day |
Tue 1/18/00 |
Tue 1/18/00 |
30 |
Draft 1st Client Status Report
|
8 days |
Tue 1/25/00 |
Thu 2/3/00 |
31 |
Team Design Reviews
|
3 days |
Tue 2/1/00 |
Thu 2/3/00 |
32 |
Team Design Reviews
|
5 days |
Mon 3/27/00 |
Fri 3/31/00 |
33 |
Faculty Advisor Meetings 1
|
1 day |
Mon 10/25/99 |
Mon 10/25/99 |
34 |
Faculty Advisor Meetings 2
|
1 day |
Wed 10/27/99 |
Wed 10/27/99 |
35 |
Faculty Advisor Meetings 3
|
1 day |
Mon 11/8/99 |
Mon 11/8/99 |
36 |
Faculty Advisor Meetings 4
|
1 day |
Mon 11/29/99 |
Mon 11/29/99 |
37 |
Faculty Advisor Meetings 5
|
1 day |
Thu 12/2/99 |
Thu 12/2/99 |
38 |
Communication with client 1
|
5 days |
Mon 10/18/99 |
Fri 10/22/99 |
39 |
Communication with client 2
|
1 day |
Tue 11/30/99 |
Tue 11/30/99 |
40 |
Hardware
|
15 days |
Mon 11/22/99 |
Fri 12/10/99 |
41 |
Component Selection
|
15 days |
Mon 11/22/99 |
Fri 12/10/99 |
42 |
Software
|
125 days |
Mon 10/11/99 |
Fri 3/31/00 |
43 |
Microcontroller Programming
|
125 days |
Mon 10/11/99 |
Fri 3/31/00 |
44 |
Demonstration
|
1 day |
Fri 4/28/00 |
Fri 4/28/00 |
45 |
Design Conference
|
1 day |
Fri 4/28/00 |
Fri 4/28/00 |
46 |
Final Demonstration
|
1 day |
Fri 4/28/00 |
Fri 4/28/00 |
47 |
Presentation
|
139 days |
Mon 10/11/99 |
Thu 4/20/00 |
48 |
Class Presentation #1
|
1 day |
Mon 10/11/99 |
Mon 10/11/99 |
49 |
Class Presentation #2
|
1 day |
Fri 11/5/99 |
Fri 11/5/99 |
50 |
Presentation of project status
|
4 days |
Mon 2/21/00 |
Thu 2/24/00 |
51 |
Presentation of project status
|
4 days |
Mon 4/17/00 |
Thu 4/20/00 |
52 |
Purchasing
|
2 days |
Fri 12/10/99 |
Mon 12/13/99 |
53 |
Bill of Materials/Purchased
|
2 days |
Fri 12/10/99 |
Mon 12/13/99 |
54 |
Promotion
|
87 days |
Thu 10/14/99 |
Fri 2/11/00 |
55 |
Web Page
|
87 days |
Thu 10/14/99 |
Fri 2/11/00 |
56 |
Complete Members Page
|
82 days |
Thu 10/14/99 |
Fri 2/4/00 |
57 |
Project Desription
|
82 days |
Thu 10/14/99 |
Fri 2/4/00 |
58 |
Project Schedule
|
82 days |
Thu 10/21/99 |
Fri 2/11/00 |
59 |
Post Documents
|
82 days |
Thu 10/21/99 |
Fri 2/11/00 |
60 |
Advertise Web Page
|
76 days |
Fri 10/29/99 |
Fri 2/11/00 |
61 |
Project Control
|
11 days |
Mon 11/22/99 |
Mon 12/6/99 |
62 |
Cost Analysis
|
8 days |
Mon 11/22/99 |
Wed 12/1/99 |
63 |
Proposal Submission
|
1 day |
Mon 11/29/99 |
Mon 11/29/99 |
64 |
Proposal Approval
|
1 day |
Mon 12/6/99 |
Mon 12/6/99 |
65 |
Research
|
37 days |
Mon 10/11/99 |
Tue 11/30/99 |
66 |
I/O Interface
|
26 days |
Mon 10/11/99 |
Mon 11/15/99 |
67 |
Linear/DSP
|
37 days |
Mon 10/11/99 |
Tue 11/30/99 |
68 |
Programmable Gain Amplifier
|
26 days |
Mon 10/11/99 |
Mon 11/15/99 |
69 |
Digital to Analog Converter
|
26 days |
Mon 10/11/99 |
Mon 11/15/99 |
70 |
Analog to Digital Converter
|
26 days |
Mon 10/11/99 |
Mon 11/15/99 |
71 |
Microprocessor
|
16 days |
Mon 10/11/99 |
Mon 11/1/99 |
72 |
Travel
|
1 day |
Fri 11/12/99 |
Fri 11/12/99 |
73 |
Tucson trip to Dataforth
|
1 day |
Fri 11/12/99 |
Fri 11/12/99 |