Software Deveolpment Schedule - Second Semester

Name Duration Start Finish Resource Names Predecessors
Coding35.00dMon 1/12/98Fri 2/27/98Mike
Detailed Development Schedule1.00dThu 1/29/98Thu 1/29/98Jonah
TDR11.00dThu 2/5/98Thu 2/5/98Tomy
Detailed Test Plan1.00dTue 2/24/98Tue 2/24/98Mike
Spring Break5.00dMon 3/2/98Fri 3/6/98Team
Status Review1.00dTue 3/3/98Tue 3/3/98Thom
TDR21.00dThu 3/5/98Thu 3/5/98Tomy6
Integration15.00dMon 3/9/98Fri 3/27/98Jonah1
Testing20.00dMon 3/30/98Fri 4/24/98Mike8
TDR31.00dTue 3/31/98Tue 3/31/98Tomy
Design Conference.1.00dFri 4/24/98Fri 4/24/98Thom
Reading Week5.00dMon 4/27/98Fri 5/1/98Team
Final Software Delivery1.00dThu 4/30/98Thu 4/30/98Jonah
Team Notebook1.00dThu 4/30/98Thu 4/30/98Tomy
As-Built report1.00dThu 4/30/98Thu 4/30/98Team