Name | Duration | Start | Finish | Resource Names | Predecessors |
---|---|---|---|---|---|
Coding | 35.00d | Mon 1/12/98 | Fri 2/27/98 | Mike | |
Detailed Development Schedule | 1.00d | Thu 1/29/98 | Thu 1/29/98 | Jonah | |
TDR1 | 1.00d | Thu 2/5/98 | Thu 2/5/98 | Tomy | |
Detailed Test Plan | 1.00d | Tue 2/24/98 | Tue 2/24/98 | Mike | |
Spring Break | 5.00d | Mon 3/2/98 | Fri 3/6/98 | Team | |
Status Review | 1.00d | Tue 3/3/98 | Tue 3/3/98 | Thom | |
TDR2 | 1.00d | Thu 3/5/98 | Thu 3/5/98 | Tomy | 6 |
Integration | 15.00d | Mon 3/9/98 | Fri 3/27/98 | Jonah | 1 |
Testing | 20.00d | Mon 3/30/98 | Fri 4/24/98 | Mike | 8 |
TDR3 | 1.00d | Tue 3/31/98 | Tue 3/31/98 | Tomy | |
Design Conference. | 1.00d | Fri 4/24/98 | Fri 4/24/98 | Thom | |
Reading Week | 5.00d | Mon 4/27/98 | Fri 5/1/98 | Team | |
Final Software Delivery | 1.00d | Thu 4/30/98 | Thu 4/30/98 | Jonah | |
Team Notebook | 1.00d | Thu 4/30/98 | Thu 4/30/98 | Tomy | |
As-Built report | 1.00d | Thu 4/30/98 | Thu 4/30/98 | Team |