Software Deveolpment Schedule

Name Duration Start Finish Resource Names Predecessors
Schedule - Gantt11.00dTue 8/26/97Tue 9/9/97
Understanding of CORBA16.00dTue 8/26/97Tue 9/16/97
Software Development Plan16.00dTue 8/26/97Tue 9/16/97
Obtain Initial Requirements5.00dMon 9/15/97Fri 9/19/97
Derived Requirements4.00dWed 9/17/97Mon 9/22/97
Draft - Specs6.00dWed 9/17/97Wed 9/24/97
Build Object Model5.00dFri 9/19/97Thu 9/25/97
Review - Specs4.00dThu 9/25/97Tue 9/30/97
Specifications Document10.00dWed 9/17/97Tue 9/30/97
Obtain Java / CORBA IDE27.00dTue 8/26/97Wed 10/1/97
Detail Object Model7.00dFri 9/26/97Mon 10/6/97
Project Proposal Draft5.00dThu 9/25/97Wed 10/1/97
Project Proposal Review4.00dThu 10/2/97Tue 10/7/97
Project Proposal0.00dThu 10/9/97Thu 10/9/97
Initial Protype "Looks Like"0.00dTue 10/21/97Tue 10/21/97Team
Build Dynamic Model16.00dWed 9/17/97Wed 10/8/97
Detail Dynamic Model14.00dThu 10/9/97Tue 10/28/97
Build Functional Model16.00dWed 9/17/97Wed 10/8/97
Detail Functional Model14.00dThu 10/9/97Tue 10/28/97
Formal Presentation Draft6.00dThu 10/30/97Thu 11/6/97
Formal Presentation Review2.00dFri 11/7/97Mon 11/10/97
Formal Presentation0.00dTue 11/11/97Tue 11/11/97
Formal Design Review0.00dTue 11/11/97Tue 11/11/97Team
Design Document Draft11.00dWed 11/12/97Wed 11/26/97
Design Document Review3.00dThu 11/27/97Mon 12/1/97
Design Document0.00dTue 12/2/97Tue 12/2/97Team
Second Protype "Works Like"0.00dTue 12/2/97Tue 12/2/97Team
Project Web Site71.00dTue 8/26/97Tue 12/2/97Tomy,Mike