Schedule for September to December in 2019
We completed the initialization of our project between September 16 and October 6, and from October 6 to November 5, we finished the Technological Feasibility. From October 12 to November 17, we Finished Requirement specification. From November 6 to November 23, we finished Design Review. From November 20 to December 6, we completed the Technical Demo.
Schedule for February to May in 2020
In February, we plan to finish the function that will allow the user to specify an area and the data analysis they want. Then, in March we are going to finish the data guide and download functions. In April, we will finish the login function and communicate in depth with Dr. Jantz about the product. In May, we will improve the product, and try to develop a perfect application.