The schedule for this project will take a total of 82 working days, beginning January 12th, 2025, and ending with the final submission on May 5th, 2025. Major tasks include traffic analysis, site design, and creation of a plan set. Deliverables for this project include 30-, 60-, and 90-percent submittals, and a final submittal.
The critical path outlines the major tasks that need to be completed on time for the project to finish by May 5th. The critical path encompasses the major tasks outlined above. To elaborate, the analysis portion will take 16 days and includes obtaining TCDC data, determining future traffic volumes, and calculating the design vehicle and speed. The design portion will take 39 days and includes designing the appropriate alignment and determining site grading. The plan set creation will take 27 days and includes creating a template for the plan set, generating proposed improvements, producing drainage plan sheets, creating plan set details, and conducting an impact analysis. This is the critical path because any delay in a critical task will directly impact the project’s overall completion date. To ensure the critical path tasks are completed on or before schedule, the team will manage individual workloads and regularly check in with the team. If these tasks cannot be completed on time, the team will modify the schedule and re-evaluate other task lengths to ensure the project is completed on time.