Project Information
Project Location: Our project is located in Kachina Viallage. The figure below shows the location of our project site relative to the City of Flagstaff.
Project Constraints: The client did not want any equipment above the ground surface besides the gutter conveyance system, so our cistern had to be subterranian. The area where the water would be able to be collected was limited to the roof because the roof has the largest area for collection of rainwater. A cistern needed to be chosen that could withstand the weight of heavy equipment during construction.
Tasks: These are all of the tasks that are included with our Scope of Services. Any task that is not listed below is not required by the Altitude Engineering Staff.
Task Name | Duration | Start | Finish |
1.0 Field Evaluation | 1 Day | Mon 8/29/16 | Mon 8/29/16 |
1.1 Site Inspection |
1 Day | Mon 8/29/16 | Mon 8/29/16 |
2.0 Design Standards, Specs, and Codes | 1 Day | Mon 8/29/16 | Mon 8/29/16 |
2.1 Research Coconino County Codes |
1 Day | Mon 8/29/16 | Mon 8/29/16 |
3.0 Design Catchment System | 9 Days | Thu 9/1/16 | Tues 9/13/16 |
3.1 Roof Runoff |
2 Days | Thu 9/1/16 | Fri 9/2/16 |
3.2 Gutter Collection |
3 Days | Mon 9/5/16 | Wed 9/7/16 |
3.3 Conveyance System |
2 Days | Thu 9/8/16 | Fri 9/9/16 |
3.4 Filtration Design System |
2 Days | Mon 9/12/16 | Tues 9/13/16 |
4.0 Cistern Design | 13 Days | Wed 9/14/16 | Fri 9/30/16 |
4.1 Capacity |
1 Day | Wed 9/14/16 | Wed 9/14/16 |
4.2 Location |
1 Day | Thu 9/15/16 | Thu 9/15/16 |
4.3 Construction Material Specifications |
4 Days | Fri 9/16/16 | Wed9/21/16 |
4.4 Disinfection |
4 Days | Thu 9/22/16 | Tues 9/27/16 |
4.5 Geotechnical Evaluation |
1 Day | Tues 9/27/16 | Tues 9/27/16 |
4.6 Pump Selection and Specification |
1 Day | Thu 9/29/16 | Thu 9/29/16 |
4.7 Slab Design |
1 Day | Fri 9/30/16 | Fri 9/30/16 |
5.0 Pressure Tank | 2 Days | Mon 10/3/16 | Tues 10/4/16 |
5.1 Research Components |
1 Day | Mon 10/3/16 | Mon 10/3/16 |
5.2 Location |
1 Day | Tues 10/4/16 | Tues 10/4/16 |
5.3 Disinfection |
1 Day | Tues 10/4/16 | Tues 10/4/16 |
6.0 Bathroom Distribution Design | 12 Days | Mon 10/3/16 | Tues 10/18/16 |
6.1 Dictribution Design |
4 Days | Mon 10/3/16 | Thu 10/6/16 |
6.2 Construction Material Specifications |
2 Days | Mon 10/17/16 | Tues 10/18/16 |
7.0 Irrigation Distribution Design | 7 Days | Tues 10/18/16 | Wed 10/26/16 |
7.1 Rain Barrel Selection |
2 Days | Tues 10/18/16 | Wed 10/19/16 |
7.2 Pipe Design |
3 Days | Thu 10/20/16 | Mon 10/24/16 |
7.3 Distribution Design |
2 Days | Tues 10/25/16 | Wed 10/26/16 |