Munds Canyon Wash Pedestrian Bridge
Cash Burger, Andrew Sayer, Ryan Emerick
Department of Civil Engineering, Northern Arizona University; Flagstaff, Arizona
Conclusion
Residents of Munds Park had expressed their concern to Coconino County about the safety of pedestrians crossing Munds Canyon Wash using the existing vehicle bridge. Therefore, the objective of this design was to provide an alternative crossing over Munds Canyon Wash for pedestrian and bicyclist traffic. To accomplish this goal a new pedestrian bridge was designed to be constructed adjacent to the existing vehicle bridge. More specifically the individual tasks were to generate a site map in order to determine the location of the new pedestrian bridge, design and place the abutments for the bridge, and to select a prefabricated bridge for implementation. Design constraints for the bridge were such that all portions of the pedestrian bridge must be above or equal to the lowest point on the existing vehicle bridge corridor. The placement of the bridge was also limited to the south side of the existing vehicle bridge. The bridge spans 110 feet and has an 8 foot wide deck. The truss type selected for the design was a pony truss with Pratt layout. The design was completed for Dale Wegner, County Engineer for the Coconino County Public Works Department. Furthermore, the pedestrian bridge design was developed in correlation with the pedestrian sidewalk plans developed by Arizona Engineering-GHD.
The location of the pedestrian bridge and its abutments in relation to the existing vehicle bridge and the surrounding area can be seen on the following topographic map developed by CAR Engineering.
NAU_PrimV_CEFNS_2C.png
Designed for a max grade of 5% as per ADA Specifications
Utilities run along  Pinewood Boulevard and existing vehicle                                  bridge and were found not to be an issue for the design or construction of the abutments
Bridge will be made of Corton Steel with synthetic planking for the bridge deck.
Design cannot impede on existing flow characteristics of the wash
All limits of construction are within the Right of Way
Abutments designed to meet all codes, specifications, and standards from:
AASHTO
ADA
ACI
AISC
From the AASHTO, ADOT, and Coconino County guide specifications for design of a pedestrian bridge:
vehicle live load = 10,000 lbs. (H5-truck)
Pedestrian live load = 65 psf
Snow load = 40 psf
Wind load = 35 psf
Seismic  load =  Category C (Wind Controls)
Dead load = 54,400 lbs. 
Total Factored Load = 174,400 lbs. (Vertical)
Total Factored Load = 27,720 lbs. (Lateral)
Throughout the design process CAR Engineering's objective was maintaining professionalism while never losing sight of the main goal for this project: Ensuring Public Safety
CAR Engineering provided a safe alternative for non vehicle traffic and effectively separated vehicle and non vehicle traffic
The proposed design is within the approved project budget
Technical Advisor: Joshua Hewes, Ph.D. , P.E.
Client: Dale Wegner, P.E.
Ken Shively at SWI
Ken Godwin at Coconino County Public Works Dept.
Jon Ebers at Coconino County Public Works Dept.
Professor: Charles Schlinger, Ph.D. , P.E.
AISC Steel Construction Manual, Thirteenth Edition
 Americans with Disabilities Act (ADA)
AASHTO Pedestrian Bridge Design Manual
 Ninyo and Moore Geotechnical Report
 American Concrete Institute Code (ACI)
Das, Braja. Principles of Foundation Engineering, Sixth Edition. Toronto: Nelson, 2007.
Das, Braja. Principles of Geotechnical Engineering, Sixth Edition. Toronto: Nelson, 2007.
AASHTO LRFD Bridge Design Specifications, Third Edition 2004
ROSCOE BRIDGE COMPANY
CONTECH CONSCRUCTION PRODUCTS
Coconino County Public Works Department
Dale Wegner, PE
Ken Godwin, EIT
Jon Ebers, Project Manager
 Arizona Engineering-GHD
Pinewood Boulevard East Roadway Reconstruction and Storm Drain Plans
Pinewood Boulevard Sidewalk Plans
Pinewood Boulevard  Outlet Structure Plans
 McCormac, Jack C., and James Nelson. Design of Reinforced Concrete Seventh Edition. Hoboken, New Jersey: John Wiley & Sons, Inc., 2006.
PosterMap.bmp
Topographic Site Map
The existing outlet structure shown on the Project Site Map
was originally a modified ADOT standard single barrel box
culvert.  As part of the design, this culvert was built up using
4,000 psi concrete and capped off in order to be used as an
abutment. The shaded area of the figure below shows the
built up portion of the outlet structure. The white area is the
existing outlet structure before modification.
SECTION - BUILT - BOTH - DIMENSIONS.bmp
Built Up Outlet structure
The cost for the project includes engineering fees, materials,
and a construction cost estimate based on similar projects
throughout Arizona.
Total Cost of Project = $295,128.00
The approved budget for this project is $300,000, with 93%
being federal money. Based on CAR Engineering's cost
estimate, the project is within the approved budget.
Design By: CAR Engineering
NAU_PrimV_CEFNS_2C.png
Abstract
Project Site Map
Design Criteria and Constraints
Capped Outlet Structure
Cost Estimate
Project Budget
Acknowledgements
References
West Abutment
Connection Detail at Outlet Structure
WEST POSTER.bmp
The west abutment is a typical spread footing design . It was
designed not to exceed an allowable soil bearing pressure of
2,000 psf. The wingwalls were designed to retain soil underneath
the approaching sidewalk. Elastomeric bearing pad was designed
to accommodate bridge thermal movements.  Lateral supports were
designed to withstand lateral loading due to wind or seismic activity.
Expansion joint is used to eliminate debris from entering between
the bridge and the abutment.
West Abutment Design
Elastomeric bearing pad was designed to accommodate bridge
thermal movements.  Lateral supports were designed to withstand
lateral loading due to wind or seismic activity. Expansion joint is
used to eliminate debris from entering between the bridge and the
abutment. A W section was used to transfer load from the bridge to
the outlet structure walls. The HSS section was used to transfer
lateral forces From the bridge to the  outlet structure walls.
Abutment Design.bmp Lateral Section Abutment.bmp
Section Abutment
Section Lateral